Sullivan West to open on time
By
TOM KANE
JEFFERSONVILLE — Sullivan West
schools will be ready to open on September 4. Scott
Bridie of Turner Construction, who is overseeing the
renovations and new construction for the Sullivan
West Central School District, reported to the Sullivan
West School Board that the three schools would be
ready.
The Narrowsburg school is the first
of the three schools to be extensively renovated.
“Demolition and construction are finished
on the first floor of the 1929 section of the building,”
Bridie said. “The second floor is complete as well.
The cafeteria, kitchen, gym and boiler room will be
completed for the first day of school. The new boiler
room will be completed by October 1, 2002. The areas
that remain to be completed are the library, art room,
nurse’s office, kindergarten and pre-K.
The work has not been without some
problems, he said. One sub-contractor fell behind
schedule but that problem has been solved. “We
will be ready to open,” Bridie said.
There will be a community walk-through
at 7:00 p.m. on Thursday, August 29.
At Jeffersonville-Youngsville, the
abatement contractor will have completed the work
scheduled for this summer before school opens. “We’ve
begun demolition in the first floor in the first four
classrooms,” Bridie said.
At Delaware Valley, abatement work
has been completed on schedule, site work renovations
have begun and the contractors have started renovation
work on the first floor.
At the new high school site, the Leeward
Company has begun clearing the athletic fields and
wetlands mitigation, preparing to seed the athletic
fields this fall, he said. Structural steel is being
erected in Section A, he said. The masonry walls in
Sector B and C are in progress and foundation work
in Sections D and E is just about completed.
The new high school is comprised of
five sectors. Sector A is the cafeteria and library,
Sector B and C is classrooms, first and second floor,
Sector D and E is the gymnasium and auditorium. Sector
A will be finished in February 2003; B and C will
be completed in May 2003 and Sectors D and E will
be completed in August 2003.
|